Managing Residential Construction Contingency

This in-depth guide covers contingency budgeting, differentiating from allowances, change order best practices, and how Bolster’s tools support transparency and budget control across every stage of the project.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
SEO for Contractors: Bolster Guide

The all-in-one software for construction contractors

Save time, win more jobs, increase profit, and get paid faster with Bolster.

Get started

Managing Residential Construction Contingency for General Contractors

General contractors in the U.S. and Canada know that surprises are inevitable in residential construction. Whether it’s hidden water damage uncovered during a renovation or a sudden spike in material costs, having a construction contingency in your budget is essential. A contingency fund is essentially the project’s emergency reserve – a financial buffer allocated for unforeseen costs that could otherwise derail a project​. In residential projects, the question is not if you'll need the contingency, but when. Experienced builders plan for surprises so that unexpected problems (e.g. discovering ancient plumbing or termite damage) don’t eat into their profit or delay the schedule​. This high-level guide will explain how to set up and manage a contingency fund effectively, communicate it to clients, differentiate it from allowances, and handle changes without breaking the budget. We’ll also highlight Bolster’s approach and tools that help contractors in the U.S. and Canada stay on budget and maintain transparency.

What is Construction Contingency (and Why It’s Important)?

Contingency funds act as a safety net for construction projects – a reserve for the “unknown unknowns” that inevitably arise during building.

In construction budgeting, contingency refers to money set aside to cover unexpected expenses or risks that were not accounted for in the initial estimate. Think of it as the project’s “rainy day fund.” It is crucial in residential projects because homes, especially remodels of older houses, often hide unforeseen issues (like mold behind walls or structural quirks) that only become apparent once work is underway. Having a healthy contingency protects both the contractor and the client: it ensures that surprises can be paid for without derailing the project’s finances​, and it minimizes the need to go back to the client for more money each time an unplanned issue arises.

A well-planned contingency is “the hallmark of a savvy construction professional”​. Without it, even a small unexpected problem can snowball into major delays or cost overruns. For example, encountering previously unknown structural damage could halt work if no funds are available to address it. By including contingency funding from the start, general contractors provide a safety margin that keeps projects running smoothly despite the inevitable curveballs. This not only protects your profit margin but also gives clients peace of mind that you have planned for the unknown. In short, contingency = risk management: it’s your safety net for walking the tightrope between underestimating (and risking a loss) and overestimating (and potentially losing bids by being too expensive)​.

Setting a Contingency Budget: How Much is Enough?

Determining the right amount for contingency is a balancing act. Set it too low and you risk budget shortfalls when surprises happen; set it too high and your bid might look uncompetitive or inflate the project cost unnecessarily. Best practice is to calculate contingency as a percentage of the project cost, adjusted for the project’s complexity and risk factors. A common rule of thumb is to start around 5–10% of the total project cost for new construction, and 10–20% for remodeling projects​. Remodeling older homes leans toward the higher end of that range – older structures are more likely to have “surprises lurking behind those vintage walls.”

Keep in mind that every project is unique. Consider the specific risk profile: for example, building an addition in a region with unpredictable weather or working on a century-old townhouse with unknown modifications may justify a higher contingency. In contrast, a straightforward new-build home on a clear lot might allow a smaller contingency percentage. Both U.S. and Canadian contractors generally follow similar percentage guidelines, though terminology is the same in both countries (contingency is universally understood). If working under a Guaranteed Maximum Price (GMP) contract (common in both U.S. and Canada), the contingency might be explicitly defined within that cap as a buffer for the contractor. The key is to base the contingency on informed judgement: use past experience, consider current market conditions (e.g. fluctuating material costs), and even leverage estimating tools that can analyze risk. For instance, Bolster’s estimating software uses historical data and real construction cost items to help predict and allocate appropriate contingency funds more accurately.

Document your contingency as a distinct line item in the budget. This clarity helps in two ways:

  • It reminds you (and the client) that the fund is earmarked for unforeseen issues

  • It prevents the contingency from quietly getting absorbed into general costs.

By clearly setting, say, “10% Contingency = $20,000” on a $200k project, you establish upfront how much is available for surprises. This practice is standard in both U.S. and Canadian construction budgeting and sets the stage for accountable management of those funds.

Contingency vs. Allowances: Differentiate and Manage Both

It’s important not to confuse contingency funds with allowances – they are distinct budgeting tools serving different purposes. Both are often included in residential construction contracts, but they handle different kinds of “unknowns.”

  • Contingency – As described above, this is a reserve for unforeseen costs that no one could pinpoint at the start. It’s a general safety net for surprises (e.g. hidden rot, unforeseen code requirements) and is usually a percentage of the overall budget. The contractor manages it as needed for true unexpected events. Ideally, if all goes well, the contingency may remain unused (more on what to do in that case later).

  • Allowances – These are specific placeholders in the budget for particular items or selections that are known in scope but not decided in detail at contract time. In other words, allowances cover indeterminate costs for known components of the project​. For example, a contract might include a flooring allowance of $10,000 – meaning the client can choose flooring materials, with $10k set aside for that cost. If the client selects a more expensive option, they’ll pay the difference; if they choose a cheaper floor, they might save money. Contracts include monetary amounts to cover these uncertain or not-yet-specified items​.

The key difference is that allowances are for “known unknowns” (you know you will install flooring or light fixtures, you just don’t know which ones yet), whereas contingency is for true unknowns (issues or changes that were not anticipated at all). In practice, allowances should be clearly defined for each relevant category (e.g. appliances, tile, fixtures), and their amounts should be realistic. This avoids confusion later. Bolster recommends using “pre-set templates and clear allowances to save time and avoid confusion on selections across projects.” In other words, have a structured approach to allowances so the client and team know exactly what’s covered by that allowance and what happens if actual costs differ.

Both U.S. and Canadian standard contracts often list allowances separately from the base contract sum. It’s good governance to keep them separate from the contingency. Never use the contingency fund to cover an overage in an allowance item without client approval. For instance, if the client’s chosen countertops exceed their allowance, that should be handled via a change order or adjustment (since it’s an elective upgrade or scope change), not quietly taken from contingency. Conversely, if you encounter a surprise structural fix, you shouldn’t label it as an “allowance item” – it should come from contingency or result in a change order if contingency is insufficient. Keeping these funds separate and using them for their intended purposes ensures transparency and avoids muddying the financial waters of the project.

Best Practices for Managing and Using Contingency Funds

Having a contingency is only half the battle – managing it wisely is what separates profitable projects from money-losers. Here are some best practices for contingency governance (i.e. how you control and utilize that reserve):

  • Establish Clear Usage Protocols: Define what qualifies as a contingency expense up front. Generally, contingency should not be used for elective upgrades, additional scope the homeowner requests, or to cover mistakes/inefficiencies. It is meant for true unknown conditions or events outside the contractor’s control​. For example, repairing unexpected termite damage or replacing a suddenly recalled electrical component can be valid contingency uses – whereas a client’s request to add recessed lights in the living room is a scope change (not to be taken from contingency). By setting these rules, you govern the fund so it isn’t treated as a slush fund. Communicate these rules to your project managers and accounting team so everyone internally knows when tapping the contingency is appropriate.

  • Require Documentation for Every Use: Anytime you do spend from the contingency, record what it was used for and why. Treat it almost like its own mini-budget. Good practice is to log a brief description (e.g. “03/15/25: Used $1,200 from contingency to relocate unforeseen plumbing in wall, per discovery during demolition”) and track the remaining balance. This log can be shared with clients to maintain trust (more on transparency later). Bolster’s platform, for instance, keeps an audit trail of changes and expenses, so you can easily note when contingency funds are allocated and have a historical record​. Such records prevent misunderstandings and ensure the funds are truly serving their purpose.

  • Get Approval for Major Drawdowns: While minor contingency uses for urgent issues may not require formal client sign-off (depending on your contract terms), it’s wise to inform the client (and get approval if appropriate) for any significant expenditure from contingency. Many contracts in North America stipulate that the contractor can use contingency up to a certain amount without approval, but above that, client notification is required. Even if not explicitly required, seeking the homeowner’s acknowledgment when, say, half the contingency needs to be used to address a structural issue, is part of good governance. It keeps clients in the loop and avoids surprises on the final bill.

  • Monitor Contingency Throughout the Project: Don’t just set the contingency at the start and forget it. Track how much is left as the project progresses, and include that in your regular budget reviews. A best practice is to incorporate contingency status in your project meetings: e.g. “Contingency started at $20k; we’ve used $5k so far on unforeseen electrical upgrades, leaving $15k.” This keeps everyone aware of how much safety net remains. If you find you’re burning through contingency faster than anticipated early in the project, that’s a red flag to investigate why. Perhaps the initial estimate missed something significant, or perhaps multiple surprises have popped up. Early detection of such issues allows you to strategize – you might need to tighten cost control on other parts of the project, or in extreme cases, discuss supplementing the contingency with the client if truly necessary. Remember the advice: catch small problems before they become big ones. Ongoing tracking makes that possible.

  • Avoid Contingency Creep: One subtle pitfall is using contingency for convenience or minor shortfalls elsewhere. For example, if a particular trade’s work came in slightly over budget, one might be tempted to cover the gap with contingency funds “just this once.” This erodes the buffer for genuine surprises and can become a habit. Discipline is key – stick to using contingency only for qualifying unforeseen conditions, not as a cushion for poor estimating or minor budget misses in other categories. If a pattern of overruns in certain budget lines emerges, address the root cause (maybe pricing was off or productivity is down) rather than silently backfilling with contingency.

By following these governance practices, a general contractor can ensure the contingency fund truly serves its purpose: it mitigates risk without incentivizing lax budgeting elsewhere. Strong contingency management is part of professional project control, and it contributes to a project finishing on budget and on good terms with the client.

Communicating Contingency to Clients: Transparency Builds Trust

Money can be a sensitive topic with homeowners, which is why transparency about the contingency from day one is non-negotiable. General contractors should clearly explain to clients what the contingency is, why it’s included in the budget, and how it will be used. This conversation typically happens during contract negotiation or the final budgeting phase before work begins. For example, you might say: “We’ve included a 10% contingency ($20,000) in the budget. This is not extra profit or a cushion for us; it’s strictly set aside for unexpected issues like hidden damage or scope changes due to unforeseen conditions. If we need to use it, we’ll discuss it with you and document why. If we don’t use it, the money remains yours (or we can apply it to other improvements if you choose).” Such an upfront discussion sets the right expectations and shows the client you’re not arbitrarily padding the budget – you’re protecting the project.

Here are some tips for keeping clients informed about contingency and maintaining transparency:

  • Show It in the Estimate: When you present the project estimate or bid, list the contingency as a separate line item (with a brief description). Modern estimating tools like Bolster’s interactive construction quotes make this easy and visually clear, helping clients understand what they’re looking at​. Instead of burying contingency in each line item’s unit prices, explicitly calling it out builds trust. The client sees that you’ve planned responsibly. In both the U.S. and Canada, sophisticated clients and architects will expect to see a contingency line in proposals – its absence might even be a red flag for inexperience.

  • Use Plain Language: Avoid jargon when explaining contingency to a homeowner. Terms like “contingency allowance” might confuse clients (and misuse of the word "allowance" can further muddle it). Simply call it an “Emergency Fund for Unforeseen Issues” in layman’s terms if needed, and provide examples (e.g. “if during the work we find something like hidden mold, this fund is there to take care of it without needing to stop the project to renegotiate finances”).

  • Regular Updates on Budget Status: Incorporate contingency usage into your regular client updates. For example, during a bi-weekly meeting or report, you might include a note: “Contingency remains at $15,000 (25% used to address unexpected foundation crack repair).” If something has arisen that requires using some of the contingency, tell the client immediately, explain the impact, and how you plan to address it. Homeowners will be far more upset discovering a cost overrun after the fact than they will be if you are upfront the moment an issue is discovered. Even if the news is unwelcome (e.g. a delay and extra cost due to something unforeseen), clients appreciate honesty and a solution-oriented approach. Transparency like this prevents the “lack of communication” pitfall that can breed mistrust​. In Canada and the U.S. alike, open communication is a professional must-do; it can also protect you legally by creating a documented history of disclosures and client acknowledgments.

  • Leverage Client Portal Tools: If you’re using project management software with a client portal, take advantage of it to keep the client in the loop. Bolster’s client portal, for instance, allows homeowners to access real-time updates and view financial information about their project anytime​. They can see budget status, change orders, and even contingency usage if you share that data. This kind of transparency fosters trust and reduces anxiety for clients. It’s often said that informed clients are happy clients. By letting them see behind the curtain (within reason), you demonstrate that there’s nothing to hide. Even without a dedicated portal, make sure to send written updates or hold periodic meetings to discuss budget and contingency status.

  • End-of-Project Honesty: When the project is wrapping up, address the contingency one last time. If there are unused contingency funds, discuss how they will be handled. In many cases, any remaining contingency belongs to the client – you should be prepared to credit it back or discuss applying it to a wish-list item that was deferred. This contingency closeout conversation is a prime opportunity to build goodwill. As one expert notes, “Any remaining funds can be discussed with the client – sometimes returning a portion, or potentially covering last-minute changes. This transparency builds immense trust”​. Clients will remember that you didn’t just find a way to spend the leftover money needlessly. Instead, by being upfront and fair, you increase your chances of referrals and repeat business​. Conversely, if the contingency is fully spent (or even exceeded), walk the client through exactly what issues it covered. A detailed breakdown of “Contingency was used for A, B, and C unforeseen issues” reinforces that the fund was used wisely.

In summary, communication is key. From the initial budgeting phase to the final invoice, keep the client informed about the contingency. Transparency doesn’t imply weakness; it shows professionalism. By demystifying how you manage their money, you prevent small concerns from turning into major distrust. Many costly conflicts or legal disputes in construction stem from poor communication – and as noted, many costly mistakes (like blown budgets) can be traced back to someone not understanding the plan or changes. Don’t let that happen on your project: communicate, document, and be transparent every step of the way.

Handling Change Orders Without Blowing the Budget  

Changes are a fact of life in construction. Even with a well-planned contingency, you will likely encounter change orders in your projects – whether due to owner requests or unexpected site conditions that alter the scope. How you handle these changes determines whether your contingency is sufficient and your project stays profitable. Best practices for change order management go hand-in-hand with good contingency planning:

  • Separate Change Orders from Contingency (When Appropriate): A change order is a formal modification to the contract scope, cost, or timeline​. Not every change will use contingency funds. In fact, many change orders are client-driven upgrades or alterations (new design choices, additional features) – these should typically be paid by the client as an extra, not out of the contingency. Contingency is not meant to subsidize the client’s wish list; it’s for unforeseen problems. Make this clear in your contract: distinguish between “changes requested by owner” and “unforeseen conditions” and outline how each is handled financially. For owner-requested changes, a change order will usually increase the contract price (and possibly include an added fee or markup). For unforeseen conditions, if you have contingency funds, you might apply those funds via a change order (essentially transferring money from the contingency line to the affected work line) with the client’s acknowledgment. If the contingency doesn’t cover it fully, then a change order would cover the additional cost beyond contingency. The goal is to ensure no ambiguity: the client should know when they are approving a use of contingency versus when they are approving an additional expense on top of the contract.

  • Have a Robust Change Order Process: Develop a step-by-step workflow for change orders and follow it consistently​. For example, the process might be: identify the need for change → document the scope and cost impact → get written client approval → perform the work → update the budget/schedule accordingly. By formalizing this, you avoid the trap of doing work on a verbal go-ahead or under informal circumstances that lead to disputes later. Each change order should clearly itemize the description of the change, the reason for it, and the cost/time implications​. Using standardized templates can ensure no details are missed. Bolster’s change order management features can help by automatically generating professional change order documents from your estimate revisions, prompting you to obtain approvals digitally. Embracing such tools ensures that every change – whether drawing from contingency or not – is properly documented and approved by all parties.

  • Track Changes and Budget Impacts in Real Time: It’s easy to lose track when multiple change orders start flying. Maintain a centralized change order log that lists all change orders, their dollar amounts, and whether they were covered by contingency or added to the contract value. This log is invaluable for preventing cost overruns; it gives you and the client an at-a-glance view of how much the original contract has changed. For instance, if several small change orders have cumulatively added 5% to the project cost, both you and the client should be aware of that running total. This can also inform whether you need to replenish contingency (in case many unforeseen changes consumed it early). Bolster’s software provides instant visibility into project changes with real-time tracking – a feature that acts like an early warning system. If an unexpected change arises (e.g. a hidden structural issue), you can simulate its impact on the budget immediately. Perhaps you see that using contingency will cover it, but leave little left; you can then have a proactive discussion with the client about increasing contingency or being extra cautious moving forward. North American contractors often say that proper change order tracking is what separates a smooth project from a chaotic one. It’s a best practice on both sides of the border to ensure every change is logged in writing.

  • Communicate Changes Promptly and Clearly: As mentioned in the communication section, transparency is vital. The moment a potential change (especially one incurring extra cost) is identified, communicate this to the client. Outline their options and the cost/time trade-offs. For example: “We found an issue with the soil grading. We can address it by doing X, which will cost approximately $5,000 and add one week. I’ll prepare a change order for your approval. We can use the contingency for this, which currently has $8,000 remaining, so no additional payment would be needed unless other issues arise.” This kind of clarity helps the homeowner feel in control and part of the decision-making, rather than feeling presented with a bill after the fact. It also demonstrates that you are on top of the situation. Effective communication and collaboration are crucial in managing change orders​ – involve the client and relevant stakeholders in discussions so that everyone understands the why and how of each change. In Canada, for instance, standard practice under CCDC contracts is to issue a “Change Order” or “Change Directive” document for signature; similarly, AIA contracts in the U.S. have formal change order forms. Use these mechanisms as they are there to protect all parties.

  • Protect Your Profit and Schedule: Not all changes are created equal – some might have no cost but delay the schedule, others vice versa, many both. As the contractor, guard against scope creep that isn’t accounted for. Bolster’s platform helps by ensuring revisions and change orders are tied back to your estimate and schedule automatically​. For example, if a client selection change happens, Bolster can auto-generate a change order and update the schedule if that selection had timeline implications. This kind of integration means you’re less likely to miss the ripple effects of a change. Every change order should preserve (or update) your profit expectations – never do additional work without adjusting the price or explicitly deciding to absorb it. One of the common business mistakes is letting small changes pile up uncharged, eroding profit margins. By using a disciplined change order process, you eliminate costly scope creep (as Bolster aptly puts it).

In essence, contingency and change orders are two sides of the coin of project change management. Use contingency for the truly unforeseen within the project scope, and use change orders for definable scope changes (especially client-initiated ones or large unforeseen issues that exceed contingency). Following the practices above will ensure that changes are handled systematically, transparently, and without financial trauma to your project. As a result, you’ll maintain control of the budget and timeline, even as you adapt to the realities on the ground.

Leveraging Tools and Technology (Bolster’s Approach to Contingency Management)

Managing contingency and budgets manually can be complex. Fortunately, modern construction management software can be a game-changer for general contractors looking to stay on top of project finances. Bolster’s platform, in particular, embodies many of the best practices we’ve discussed by providing features and workflows that enforce discipline, transparency, and real-time tracking. Here are a few ways Bolster’s tools and philosophy can help with contingency and overall budget management:

  • Accurate Estimating with Risk Factoring: The foundation of a good contingency is a solid estimate. Bolster’s estimating software provides access to a vast database of real construction costs (100+ million items) and assemblies, which helps contractors build highly accurate estimates quickly. By reducing guesswork, you start with a more reliable budget. The software also allows you to easily add a contingency line item and adjust its percentage. Bolster understands that predicting and allocating funds for the unknown is challenging, so the platform encourages data-driven estimation. As noted in the Bolster blog, having the right tool makes contingency planning far more accurate. In practice, this means you can justify your contingency figure to clients with confidence, perhaps even showing historical data or similar projects to back it up.

  • Interactive Proposals and Allowance Management: Bolster enables you to create interactive quotes and presentations for clients​. Instead of a static PDF, clients can see a dynamic breakdown of costs, including allowances and contingency. This interactivity demystifies the budget – for instance, clients could toggle options or see the impact of different allowance choices (which helps avoid later allowances surprises). Bolster’s approach to selections and allowances also helps differentiate them from contingency: you can set up selection templates with clear allowances for items like finishes, so the client’s choices are tracked against those allowances in real time​. The platform will show if a selection goes over the allowance and can even prompt a change order for the difference, rather than dipping into any contingency. This reinforces the discipline that allowances are separate, while giving both you and the client immediate visibility into those costs.

  • Real-Time Budget Tracking & Alerts: Perhaps one of the biggest advantages of Bolster (and similar software) is the ability to track your project budget in real time. Every expense or budget change entered is reflected in up-to-date reports and dashboards. Imagine you’re halfway through a project: Bolster can tell you that you’ve spent, say, 50% of the budget while 60% of the work is completed – indicating you’re under-spending, or vice versa​. If you’re, for example, 80% through the budget but only 50% through the work, the software will make that discrepancy glaringly obvious. This acts as an early warning system. Instead of discovering at the end that you blew through contingency and then some, you’d get visual cues and can be proactive. Bolster can even send alerts for budget thresholds or when changes occur. By integrating the schedule with the budget, the platform can notify you if a delay (say a slip in the schedule) might cause additional costs, or if a budget item is trending over. This continuous oversight aligns with the advice to monitor progress and finances actively, not take a “set it and forget it” approach​.

  • Change Order Automation and Scope Control: Bolster’s system automatically generates revisions and change orders when you make changes to the project scope in the platform. It prompts you to get new approvals for those changes, thereby preserving your profit on every job (as Bolster advertises)​. By using the software to log a change, you ensure it’s not lost in the shuffle. The platform maintains a central log of all change orders and their statuses, so you and your client can see what’s been approved and what’s pending. Moreover, because Bolster links selections to the schedule and budget, if a client’s choice triggers a change, it can auto-update timelines and budgets accordingly​. This level of integration means no more forgetting to charge for a change or update the finish date – the tool helps enforce the process. It essentially bakes the best practices (documentation, client sign-off, budget adjustments) into the workflow, reducing the chance of human error. As a result, scope creep is kept in check and contingencies are used intentionally, not accidentally drained by unchecked changes.

  • Client Portal and Transparency Features: Bolster’s client portal is designed to keep homeowners informed and engaged. It offers clients a window into the project – they can see progress photos, schedule updates, and yes, budget information such as allowances used or remaining​. This fosters a spirit of openness. Instead of periodic awkward conversations about money, the client can self-service some of that information at any time. The portal’s budget tracking feature can show clients how much contingency has been used and for what (if you choose to share that detail)​. By giving clients this visibility, Bolster helps build trust and reduce miscommunication. Clients are less likely to be surprised or feel in the dark, since the data is at their fingertips. It’s worth noting that providing such transparency is a relatively new trend – one that Bolster champions – and it is enhancing client-contractor relationships by avoiding the old “mysteries” of construction costs. A transparent platform can also protect contractors: with everything documented, there’s a clear record to refer back to if any disputes arise about how the contingency was used or why a change order was issued.

  • Philosophy of Proactive Management: Underlying Bolster’s tools is a philosophy that mirrors what top contractors do: plan thoroughly, communicate clearly, and adjust in real time. The software encourages you to take a proactive stance. For instance, Bolster’s dashboards and analytics can show profitability projections as the job progresses, factoring in any use of contingency or change orders. This means you’re never flying blind – you can make informed decisions swiftly to keep the project on track​. In both the U.S. and Canada, adopting such a data-driven, transparent approach is increasingly seen as the future of construction management. Bolster is essentially providing the “safety net” and centralized control center that helps even small contracting businesses manage projects with the rigor of a much larger operation​. By centralizing project data and communication, Bolster minimizes the risk of oversight and ensures everyone stays on the same page​ – which is exactly what you need to manage contingency and changes effectively.

In conclusion, using a platform like Bolster can significantly simplify contingency management. While no software can replace the contractor’s judgment and experience, it can greatly reduce human error and oversight by automating best practices. The result is that you catch issues early, handle changes smoothly, and keep the project profitable. Whether you’re a general contractor in New York or in Toronto, the principles remain the same – and the right tools help ensure you execute those principles consistently.

Conclusion

Managing residential construction contingency is both an art and a science. It requires foresight to budget appropriately, discipline to use the funds correctly, and transparency to keep everyone on board. By understanding what contingency is and keeping it distinct from allowances and planned costs, you set a strong foundation for financial control. Implementing best practices – from establishing clear protocols and documenting every contingency use to maintaining open communication with clients – will guard against misunderstandings and cost overruns. And when changes come knocking (as they always do), a robust change order process will ensure you adapt without losing grip on the budget or eroding the contingency reserved for true surprises.

General contractors in the U.S. and Canada who master contingency management tend to see smoother projects and happier clients. They avoid the common pitfalls of busted budgets and eroded trust. As we’ve highlighted, modern tools like Bolster can reinforce these good habits by bringing real-time visibility and automation to your process. But even with the best software, it’s the mindset of preparedness and honesty that truly defines success in managing contingencies. Be prepared for the worst, communicate at your best, and you’ll navigate the uncertain waters of residential construction with confidence. In the end, a well-managed contingency doesn’t just save money – it elevates your reputation as a contractor who delivers on promises, rain or shine, planned or unplanned.

Win jobs effortlessly and automate your admin

General contractors using Bolster are, on average, winning 15% bigger jobs, 20% more often.

Hours of estimating, completed in minutes

Create accurate and detailed estimates in minutes, no matter what type of work you do. Estimate with templates pre-built with your items, costs, and profit, and automate your item and labor costing with AutoCost.
Dashboard mockup

Close deals on the spot with presentations

First impressions matter. Compete on professionalism rather than just price with automatically generated presentations that help contractors close 20% more jobs on average.
Dashboard mockup

Give your customers the power of choice

Make more profit with optional items, upgrades and selections so your customers can upgrade themselves without an awkward phone call -- or any extra work for you.
Dashboard mockup

Generate your material list, budget and schedule

Setting up all your jobs is a part-time job in itself -- but in Bolster the budget and schedule generate automatically from the estimate. It's fully customizable of course -- but without any of the up-front repetitive work.
Dashboard mockup

Accept payments online

Send payment requests through the client portal on task completion, which can be paid with debit & credit card or secure bank transfer. Skip long check clearing times, and get payments deposited instantly into your Bolster Business Account.
Dashboard mockup
"Not only do we win a lot of extra jobs, Bolster allows us to be much more profitable. We 10x'ed our business since starting with Bolster."
Matthew Ashley
Matthew Ashley
Basement Builders
"Now that we're using Bolster, just the professionalism and the presentation it gives our quotes, we're taking business from our more established competitors."
Taylor Hix
Taylor Hix
Bigfoot Outdoor Living
"The best part about the quotes is upselling without even trying. Using Bolster, I don't feel like a greasy used-car salesman trying to get the most profit out of every job - customers are selecting more expensive options themselves!"
Robert Hatfield
Robert Hatfield
Hatfield Flooring LLC
"If you're willing to invest in your business and work with Bolster, you're going to exceed your expectations of what you can achieve. If you put in the work, you'll see a return on your investment quickly."
Che Whitaker
Che Whitaker
Patriot Fencing
"The fact we can have clients picking their own finishes -- amazing! It's a huge time saver for us -- we used to go to client's houses with boxes of samples and we don't have to do that anymore."
Chris Profile Cabinetry
Chris
Profile Cabinetry
"I used to be the guy who would list 10-15 items and there here's your price. Now, I look at it and tell people it's like going to the grocery store. That's what we give you - no questions, no surprises."
Peter Farris
Pete Farris
Epic Remodelers

"If you're willing to invest in your business and work with Bolster, you're going to exceed your expectations of what you can achieve. If you put in the work, you'll see a return on investment quickly."

Che Whitaker
Owner, Patriot Fencing

Ideal for builders, renovators, subcontractors and more

Thousands of companies just like yours prefer Bolster.

Custom homes
Garages
Fences
Roofing
Additional dwelling units
Decks
Pools
Home renovations
Cabinets
Additions
Painting
Stucco
Siding
Windows and doors
Epoxy
Flooring
Textures and finishing
Bathrooms
Kitchens
Solar
Sunrooms
Tile
Countertops
Masonry
Hardscape
Concrete
Landscaping
Upstarts - $200k - 500k
Stable - $500k - $1m
Scale ups - $1m - $5m
Growth - $5m - $20m
Established - $20m+

What would you do with more time and more profit?